Work Period in NSW Payment Claims

📅 Updated: July 2025 ⏱️ 8 min read 📋 Payment Claim Best Practices

⚠️ Compliance Warning

Failing to properly specify the Work Period or aligning it with a valid Reference Date can invalidate your entire payment claim under the Security of Payment Act.

1. Field Name and Definition

The Work Period is the specific timeframe during which the construction work being claimed was performed or the related goods and services were supplied. This field identifies the chronological boundaries of the work that forms the basis of your payment claim.

This field appears on a Payment Claim to establish a clear temporal connection between the construction activities performed and the payment being sought. It provides a critical reference point for all parties to understand exactly which work is being claimed in the current payment application.

3. Practical Guidance

Step-by-step Instructions for Completing this Field

  1. Identify the applicable time period: Review your site diaries, progress reports, and project records to determine the exact dates when the claimed work was performed.
  2. Check the contract: Your construction contract may specify how work periods should be defined (e.g., calendar months, 4-week periods, or milestone-based).
  3. Format the dates correctly: Express the Work Period clearly using the Day Month Year format (e.g., "1 June 2025 to 30 June 2025").
  4. Ensure consistency: The Work Period should align with your reference date and the timing provisions in your contract.
  5. Be specific: Avoid vague terminology like "recent works" or "ongoing works" - always provide exact dates.

Where to Find this Information

The information required to complete the Work Period field can be found in:

  • Project programming documents
  • Site diaries and daily logs
  • Timesheets and labour records
  • Delivery receipts for materials
  • Meeting minutes documenting progress

4. Common Mistakes and How to Avoid Them

Typical Errors

  • Overlapping work periods: Including days that were claimed in previous payment applications.
    Solution: Maintain a register of all payment claims and their respective work periods.
  • Claiming for work outside the statutory timeframe: Making claims for work completed more than 12 months ago.
    Solution: Implement a tracking system to ensure timely claims.
  • Vague or missing work periods: Failing to specify exact dates.
    Solution: Always include specific start and end dates for the work period.
  • Misalignment with reference dates: The work period not aligning with contractual reference dates.
    Solution: Understand how your contract defines reference dates and ensure your work periods align.

Impact on Payment Claim Validity

Any of these errors can potentially render your payment claim invalid or significantly weaken your position in a dispute. Courts and adjudicators have consistently held that proper identification of when work was performed is an essential element of a valid payment claim.

5. Risks of Not Including This Information

Risk Type Description
Legal Risks Your payment claim may be deemed invalid under Section 13(2)(a) for failing to properly identify the work. You may also lose the right to claim for work that falls outside statutory timeframes.
Financial Risks Delayed payment due to respondents rejecting claims with unclear work periods, and potential loss of entitlement to payment for work not properly identified.
Dispute Risks Ambiguity about which work is being claimed increases the likelihood of disputes and gives respondents legitimate grounds to refuse payment if they cannot determine what is being claimed.
Adjudication Risks Adjudicators may give less weight to claims with ambiguous work periods, and the determination may be vulnerable to challenge in court if jurisdiction cannot be established.

6. Examples

Example 1: Standard Monthly Claim

Work Period: 1 June 2025 to 30 June 2025
Reference Date: 30 June 2025

Example 2: Milestone-Based Contract

Work Period: 15 May 2025 to 22 June 2025
Milestone: Completion of Building Envelope (Stage 3)
Reference Date: 25 June 2025

Example 3: Civil Works

Work Period: 1 June 2025 to 30 June 2025
Sections: Chainage 450-780 Road Formation and Drainage Works

8. Frequently Asked Questions

Q: Can I include work from multiple periods in a single payment claim?
A: Yes, the Act permits including work from multiple periods in a single claim. Section 13(6) specifically allows including amounts that have been the subject of previous claims. However, you must clearly identify which work was performed in which period to avoid confusion.
Q: If my contract doesn't specify payment periods, how do I determine the Work Period?
A: If your contract is silent on payment periods, the Act creates statutory reference dates on the last day of each named month. Your Work Period would typically be that month, with the reference date being the last day of the month.
Q: Does maintenance or defect rectification work count as "construction work" for establishing the Work Period?
A: Yes, rectification work performed under the contract can constitute "construction work" for the purposes of the Act. This can be important for establishing that work was performed within the 12-month statutory timeframe.
Q: Can I make a claim for a Work Period in which no physical work was performed but materials were delivered to site?
A: Yes. The Act covers both "construction work" and "related goods and services." The supply of materials for the project constitutes "related goods and services" and can form the basis of a valid claim, even if no physical construction occurred in that period.

Never Miss a Reference Date Again

Our advanced automated system automatically calculates and tracks your reference dates, ensuring every payment claim is served on time, every time.

Schedule Demo
Standardised CTA Section

Contract Administration for NSW Construction

Our team provides strategic contract administration and project management services that streamline your workflows, improve cash flow, and reduce compliance risks.

Serving: Residential builders, commercial subcontractors, and developers across NSW construction projects

Schedule Demo