Total Payments Received to Date in NSW Payment Claims
⚠️ Compliance Warning
Incorrectly calculating or omitting this figure can create mathematical errors that may invalidate your entire payment claim under the Security of Payment Act.
1. Field Name and Definition
Total Payments Received to Date is a critical field in your NSW Payment Claim that represents the cumulative sum of all payments actually received from the respondent (principal or head contractor) from the commencement of the contract up to the date of preparing the current payment claim.
This field appears on every Payment Claim as a mandatory component under the Building and Construction Industry Security of Payment Act 1999 (NSW) because it:
- Establishes the payment history between parties
- Provides context for the current claim amount
- Enables accurate calculation of the outstanding balance
- Creates a clear audit trail for the project's financial progress
2. Legal Requirements
Statutory Framework
Under the Building and Construction Industry Security of Payment Act 1999 (NSW) ("the Act"), whilst there is no explicit requirement to state total payments received, this information is essential for establishing the "amount claimed" under section 13(2)(a).
The Act requires that a payment claim must:
- Identify the construction work or related goods and services
- Indicate the amount of the progress payment claimed
- State that it is made under the Act
Case Law Guidance
Clarence Street Pty Ltd v Isis Projects Pty Ltd [2005] NSWCA 391
The Court of Appeal emphasised that payment claims must contain sufficient information to enable the respondent to understand the basis of the claim. Including total payments received provides this essential context.
Multiplex Constructions Pty Ltd v Luikens [2003] NSWSC 1140
This case highlighted that ambiguity in payment claims can lead to invalidity. A clear statement of payments received eliminates ambiguity about the net amount being claimed.
Consequences of Incorrect Completion
Incorrectly stating or omitting total payments received can result in:
- Your payment claim being deemed invalid
- An adjudication application being dismissed
- Delays in payment while clarifications are sought
- Erosion of credibility in subsequent claims
- Potential waiver of rights to claim certain amounts
3. Practical Guidance
Step-by-Step Instructions
- Gather Payment Records: Compile all remittance advices, print bank statements showing cleared payments, and collect any payment schedules previously issued by the respondent.
- Verify Each Payment: Cross-reference remittance advices with bank deposits. Ensure GST components are correctly included and account for any retention amounts that have actually been released and received.
- Calculate the Total: Add all verified, cleared payments chronologically. Include only amounts actually received, not amounts that are promised or scheduled.
- Document Your Calculation: Create a payment summary spreadsheet. List each payment with its date and amount, and keep all supporting documentation readily available for verification.
Where to Find This Information
- Accounting System: Most construction accounting software maintains running totals of payments received.
- Bank Records: Your online banking history provides definitive proof of cleared funds.
- Project Files: Check physical or digital folders containing remittance advices.
- Email Records: Payment notifications and remittances are often sent electronically.
4. Common Mistakes and How to Avoid Them
Including Uncleared Payments
Mistake: Counting payments shown as "pending" or "processing" in your bank account.
Solution: Only include cleared funds that are actually available in your account.
Double-Counting Retention
Mistake: Including a retention amount in both the "amount withheld" and "amount received" columns.
Solution: Maintain separate tracking for retention held versus retention that has been released and paid.
Excluding GST
Mistake: Showing GST-exclusive figures when your contract sum and other claim items are GST-inclusive.
Solution: Ensure consistency in GST treatment across the entire payment claim.
Calculation Errors
Mistake: Simple manual addition errors or incorrect spreadsheet formulas.
Solution: Double-check all calculations, preferably using accounting software or having a colleague review your work.
5. Risks of Inaccurate Information
Failing to provide an accurate 'Total Payments Received to Date' figure introduces significant risks that can jeopardise your cash flow and legal standing.
| Risk Category | Description |
|---|---|
| Legal Risks | An incorrect calculation can make the entire claim mathematically inconsistent, potentially rendering it invalid under the Act and preventing you from pursuing adjudication. |
| Financial Risks | Respondents may legitimately delay payment while they seek clarification on the discrepancies, harming your project cash flow. You may also lose the right to claim interest on overdue amounts. |
| Dispute Risks | It provides the respondent with technical grounds to challenge your claim, shifting focus away from the substantive issue of payment for work performed. |
| Strategic Risks | Repeated errors undermine your professionalism and credibility, which can damage the commercial relationship and affect your position in any formal dispute resolution. |
6. Examples
Standard Progress Claim
Total Payments Received to Date: $1,852,500.00 (inc GST)
Claim Following Retention Release
Total Payments Received to Date: $4,250,000.00 (inc GST)
(Including 50% retention release of $125,000.00 received 15 March 2024)
Variation-Heavy Project
Total Payments Received to Date: $2,755,000.00 (inc GST)
(Comprising Contract works: $2,455,000.00 + Approved Variations: $300,000.00)
7. Related Fields & Consistency Checks
The accuracy of this field is checked against others in the claim. Always verify:
- Current Claim Amount: The sum of 'Total Payments Received' and the 'Current Claim Amount' should equal the total value of work claimed to date.
- Contract Sum: The total payments received, when viewed as a percentage of the total contract sum, provides a clear indicator of project progress.
- Retention Held: Ensure that payments received for released retention are correctly accounted for and not confused with retention still being held by the respondent.
8. Frequently Asked Questions
This guide is provided for general information purposes. For specific advice about your payment claim, consult a qualified construction lawyer familiar with NSW Security of Payment legislation.
Ensure Accurate Claims, Every Time
Our advanced automated system cross-references your data to prevent costly errors and ensure your payment claims are always compliant and accurate.
Schedule DemoContract Administration for NSW Construction
Our team provides strategic contract administration and project management services that streamline your workflows, improve cash flow, and reduce compliance risks.
Serving: Residential builders, commercial subcontractors, and developers across NSW construction projects
Schedule Demo