Retention Monies in NSW Payment Claims | Contracts Administrator

Retention Monies in NSW Payment Claims

📅 Updated: July 2024 ⏱️ 8 min read 📋 Payment Claim Best Practices

⚠️ Compliance Warning

Incorrectly calculating or failing to claim the release of retention monies can lead to significant cash flow issues and disputes under the Security of Payment Act.

1. Field Name and Definition

Retention Monies refers to the portion of payment withheld by the principal or head contractor from progress payments as security for the satisfactory completion of construction work and rectification of any defects during the defects liability period.

This field appears on Payment Claims to identify:

  • The total amount of retention currently held
  • When retained amounts become due for release
  • The calculation basis for retention deductions
  • Any partial releases of retention already made

Including retention monies details ensures transparency in payment calculations and helps track when these funds should be released back to the contractor.

3. Practical Guidance

Step-by-Step Instructions

  1. Review the Contract: Locate retention provisions (typically in payment clauses), identify the retention percentage (e.g., 5% or 10%), note any caps, and check for staged release provisions.
  2. Calculate Current Retention: Determine the total value of work completed, apply the contractual retention percentage, deduct any previously released amounts, and verify against any retention cap.
  3. Identify Release Triggers: Note key dates or milestones such as practical completion, the end of the defects liability period, or other specific events defined in the contract.
  4. Document Release Dates: Clearly state when retention becomes due for release, referencing the relevant contract clauses and any conditions that must be met.

Clear Presentation Format

RETENTION MONIES HELD Total Work Completed to Date: $1,250,000.00 Retention Rate (Contract Cl. 37.2): 10% Total Retention Calculated: $125,000.00 Less: Previously Released: $0.00 Current Retention Held: $125,000.00 RETENTION RELEASE SCHEDULE 50% on Practical Completion: $62,500.00 (est. 15 March 2024) 50% on Expiry of DLP: $62,500.00 (est. 15 March 2025)

4. Common Mistakes and How to Avoid Them

Typical Errors

  • Omitting retention details entirely: Always include the section, even if to state "Nil retention applicable".
  • Incorrect percentage application: Double-check contract terms, as different rates might apply to different work portions.
  • Failing to track partial releases: Maintain a detailed ledger of all retention releases and reference payment certificates.
  • Miscalculating release dates: Use actual certified dates, not estimates, and account for any defects affecting the release.

Best Practices

  • Create a dedicated retention tracking spreadsheet.
  • Cross-reference your calculations with the respondent's payment schedules.
  • Update calculations with each new payment claim.
  • Document any disputes regarding retention separately.

5. Risks of Not Including This Information

Risk Category Description
Legal Risks Claims may be rejected for being incorrectly calculated. Lack of clarity can lead to an unfavourable adjudication determination.
Financial Risks Failing to claim due retention releases directly impacts cash flow. You may also lose the right to claim interest on overdue amounts.
Dispute Risks Ambiguity increases the likelihood of payment schedule disputes, prolonging resolution times and eroding trust.
Strategic Disadvantages An unclear claim weakens your position in adjudication and reduces leverage in any settlement negotiations.

6. Examples

Standard Building Contract

Payment Claim No: 8 Retention Monies: - Work under Contract Value: $2,500,000.00 - Retention Percentage: 5% (Clause 42.3) - Maximum Retention: $100,000.00 (Clause 42.4) - Retention on Current Claim: $3,750.00 - Total Retention to Date: $100,000.00 (Cap Reached) - Due for Release: * 50% ($50,000) on Practical Completion - achieved 20 Jan 2024 * 50% ($50,000) on DLP Expiry - due 20 Jan 2025

Subcontract with Staged Release

Retention Details: - Retention Rate: 10% reducing to 5% after 50% completion - Work Completed < 50%: $400,000 @ 10% = $40,000 - Work Completed > 50%: $350,000 @ 5% = $17,500 - Total Current Retention: $57,500 - Milestone Release: $20,000 released on Stage 2 completion - Net Retention Held: $37,500

8. Frequently Asked Questions

Q1: What if the contract doesn't specify retention terms?
A: If no retention applies, clearly state "No retention applicable under this contract" in your payment claim. Never leave the field blank as this creates ambiguity.
Q2: Can I claim interest on overdue retention monies?
A: Yes, if retention is not released when due, it becomes a debt owing. Include overdue retention in your payment claim and separately calculate any contractual or statutory interest applicable.
Q3: What if the principal disputes the retention release date?
A: Document the basis for your release date (e.g., a Practical Completion Certificate), include it in your payment claim, and maintain records of any dispute correspondence. An adjudicator will determine the correct position if the matter proceeds to adjudication.
Q4: Should I show retention on variation works?
A: Unless the contract specifically excludes variations from retention, you should apply the same retention percentage to approved variations. Always check if your contract has different provisions for variations.
Q5: How do I handle retention when there are defects?
A: If the contract allows retention to be withheld for defects, clearly show the calculation and reference the relevant clause. If defects exist but don't prevent release under the contract, claim the retention as due and document any related agreements.

Automate Retention Tracking and Secure Your Cash Flow

Our platform eliminates manual errors, ensures timely claims for retention release, and keeps your projects financially healthy.

Schedule Demo
Standardised CTA Section

Contract Administration for NSW Construction

Our team provides strategic contract administration and project management services that streamline your workflows, improve cash flow, and reduce compliance risks.

Serving: Residential builders, commercial subcontractors, and developers across NSW construction projects

Schedule Demo