Due Date for Payment - Cost Plus Best Practices | Contracts Administrator

Due Date for Payment in Cost Plus Payment Claims

📅 Updated: August 2025 ⏱️ 8 min read 📋 Cost Plus Payment Claim Best Practices

⚠️ Compliance Warning

Failing to correctly calculate and state the due date can delay payment and jeopardise your right to enforce it under the Security of Payment Act.

1. Field Name and Definition

The "Due date for payment" field on a NSW Payment Claim specifies the exact date by which the claimed amount must be paid to the claimant. This date is a critical component of a payment claim as it establishes the deadline for payment and triggers important legal consequences if payment is not made by this date.

This field appears on a Payment Claim because the Building and Construction Industry Security of Payment Act 1999 (NSW) ("the Act") creates a statutory framework for ensuring timely payment for construction work. The due date provides clarity for both parties about when payment obligations must be fulfilled.

3. Practical Guidance

Step-by-Step Instructions for Completing This Field

  1. Review your construction contract: Check if your contract specifies payment terms (e.g., "14 days after submission of invoice").
  2. Calculate the due date: If your contract is silent on payment terms, use the statutory timeframes (15 business days for head contractors, 20 for subcontractors) from the date the payment claim is served.
  3. Use the correct date format: Express the due date in Day Month Year format (e.g., 15 August 2025).
  4. Ensure the date is a business day: If the calculated date falls on a weekend or public holiday, the due date becomes the next business day.

Information Required to Complete This Field

  • A copy of your construction contract.
  • The date when the payment claim is served.
  • A calendar to count business days (excluding weekends and public holidays).
  • Knowledge of whether you are a head contractor or subcontractor.

4. Common Mistakes and How to Avoid Them

Typical Errors When Completing This Field

  • Miscounting business days: Forgetting that business days exclude weekends and NSW public holidays.
  • Confusing calendar days with business days: The Act specifies business days, not calendar days.
  • Using incorrect default timeframes: Applying 15 business days when you are a subcontractor (should be 20), or vice versa.
  • Ignoring contract provisions: Not checking if your contract specifies a different (and earlier) payment timeframe.
  • Miscalculating from the wrong starting date: The counting period begins from when the payment claim is served, not when it is prepared.

How These Errors Impact Payment Claim Validity

While an incorrect due date may not automatically invalidate a payment claim, it can create significant complications, such as challenged enforcement actions or a loss of credibility in a dispute.

Best Practices to Ensure Accuracy

  1. Double-check all calculations of business days.
  2. Use a calendar to mark the date of service and count forward.
  3. Have a colleague verify your calculation.
  4. Use an automated platform that calculates due dates based on your project setup.

5. Risks of Not Including This Information

Risk Type Impact
Legal Risks Difficulty enforcing payment rights if timing requirements are not met and complications in adjudication proceedings if timeframes are disputed.
Financial Risks Delayed payments due to confusion, inability to claim interest on late payments, and cash flow disruptions.
Dispute Risks Respondents may argue they were not properly informed of payment obligations, leading to disputes over when statutory remedies become available.
Strategic Disadvantages Loss of credibility in payment disputes and a weakened negotiating position.

6. Examples

Example 1: Head Contractor to Principal (Statutory)

Date of Payment Claim: 1 August 2025
Due Date for Payment: 22 August 2025
(Calculation: 1 August 2025 + 15 business days)

Example 2: Payment to Subcontractor (Statutory)

Date of Payment Claim: 5 August 2025
Due Date for Payment: 3 September 2025
(Calculation: 5 August 2025 + 20 business days)

Example 3: Contract Specifies Earlier Timeframe

Date of Payment Claim: 10 August 2025
Contractual Term: 10 business days
Due Date for Payment: 24 August 2025
(Contract specifies 10 business days, which is earlier than the statutory timeframe and therefore applies)

8. Frequently Asked Questions

Q: What happens if the due date for payment falls on a weekend or public holiday?
A: If the calculated due date falls on a weekend or public holiday, the payment becomes due on the next business day.
Q: Can I shorten the due date for payment in my contract?
A: Yes. The Act provides maximum timeframes, but your contract can specify earlier payment dates. The Act will enforce the earlier contractual date if one exists.
Q: What if my contract states a longer payment period than the Act allows?
A: The Act prevails over any inconsistent contractual terms. If your contract specifies a longer payment period than the statutory maximum, the statutory timeframe will apply regardless of what the contract says.
Q: If payment is not made by the due date, what can I do?
A: You have several options: you may recover the unpaid amount as a debt in court, make an adjudication application, serve notice of your intention to suspend work, and you may be entitled to claim interest on the unpaid amount.

Eliminate Due Date Errors

Our automated system ensures your payment claims are always compliant, calculating the correct due date every time.

Schedule Demo
Standardised CTA Section

Contract Administration for NSW Construction

Our team provides strategic contract administration and project management services that streamline your workflows, improve cash flow, and reduce compliance risks.

Serving: Residential builders, commercial subcontractors, and developers across NSW construction projects

Schedule Demo