Due Date for Payment in Cost Plus Payment Claims
⚠️ Compliance Warning
Failing to correctly calculate and state the due date can delay payment and jeopardise your right to enforce it under the Security of Payment Act.
1. Field Name and Definition
The "Due date for payment" field on a NSW Payment Claim specifies the exact date by which the claimed amount must be paid to the claimant. This date is a critical component of a payment claim as it establishes the deadline for payment and triggers important legal consequences if payment is not made by this date.
This field appears on a Payment Claim because the Building and Construction Industry Security of Payment Act 1999 (NSW) ("the Act") creates a statutory framework for ensuring timely payment for construction work. The due date provides clarity for both parties about when payment obligations must be fulfilled.
2. Legal Requirements
Relevant Sections of the Act
Section 11 of the Building and Construction Industry Security of Payment Act 1999 (NSW) specifically addresses the due date for payment:
- For payments from a principal to a head contractor, the payment becomes due and payable 15 business days after a payment claim is made, or an earlier date if provided in the construction contract.
- For payments to a subcontractor, the payment becomes due and payable 20 business days after a payment claim is made, or an earlier date if provided in the construction contract.
- For exempt residential construction contracts, the due date is as set out in the contract terms.
Case Law
Galileo Miranda Nominee Pty Ltd v Duffy Kennedy Pty Ltd [2019] NSWSC 1157
The court determined that the "amount that is payable" under Section 16(1) is the amount specified in the payment schedule (the scheduled amount) and does not include any interest which might be payable under Section 11.
Consequences of Incorrect Completion
Incorrectly stating or omitting the due date for payment may:
- Create confusion about when payment is legally required.
- Potentially invalidate enforcement actions if undertaken before the correct due date.
- Delay your ability to pursue remedies such as adjudication, debt recovery proceedings, or suspension of work.
3. Practical Guidance
Step-by-Step Instructions for Completing This Field
- Review your construction contract: Check if your contract specifies payment terms (e.g., "14 days after submission of invoice").
- Calculate the due date: If your contract is silent on payment terms, use the statutory timeframes (15 business days for head contractors, 20 for subcontractors) from the date the payment claim is served.
- Use the correct date format: Express the due date in Day Month Year format (e.g., 15 August 2025).
- Ensure the date is a business day: If the calculated date falls on a weekend or public holiday, the due date becomes the next business day.
Information Required to Complete This Field
- A copy of your construction contract.
- The date when the payment claim is served.
- A calendar to count business days (excluding weekends and public holidays).
- Knowledge of whether you are a head contractor or subcontractor.
4. Common Mistakes and How to Avoid Them
Typical Errors When Completing This Field
- Miscounting business days: Forgetting that business days exclude weekends and NSW public holidays.
- Confusing calendar days with business days: The Act specifies business days, not calendar days.
- Using incorrect default timeframes: Applying 15 business days when you are a subcontractor (should be 20), or vice versa.
- Ignoring contract provisions: Not checking if your contract specifies a different (and earlier) payment timeframe.
- Miscalculating from the wrong starting date: The counting period begins from when the payment claim is served, not when it is prepared.
How These Errors Impact Payment Claim Validity
While an incorrect due date may not automatically invalidate a payment claim, it can create significant complications, such as challenged enforcement actions or a loss of credibility in a dispute.
Best Practices to Ensure Accuracy
- Double-check all calculations of business days.
- Use a calendar to mark the date of service and count forward.
- Have a colleague verify your calculation.
- Use an automated platform that calculates due dates based on your project setup.
5. Risks of Not Including This Information
| Risk Type | Impact |
|---|---|
| Legal Risks | Difficulty enforcing payment rights if timing requirements are not met and complications in adjudication proceedings if timeframes are disputed. |
| Financial Risks | Delayed payments due to confusion, inability to claim interest on late payments, and cash flow disruptions. |
| Dispute Risks | Respondents may argue they were not properly informed of payment obligations, leading to disputes over when statutory remedies become available. |
| Strategic Disadvantages | Loss of credibility in payment disputes and a weakened negotiating position. |
6. Examples
Example 1: Head Contractor to Principal (Statutory)
Due Date for Payment: 22 August 2025
(Calculation: 1 August 2025 + 15 business days)
Example 2: Payment to Subcontractor (Statutory)
Due Date for Payment: 3 September 2025
(Calculation: 5 August 2025 + 20 business days)
Example 3: Contract Specifies Earlier Timeframe
Contractual Term: 10 business days
Due Date for Payment: 24 August 2025
(Contract specifies 10 business days, which is earlier than the statutory timeframe and therefore applies)
7. Related Fields
Reference Date: The reference date establishes when you are entitled to make a payment claim, which then starts the calculation for the due date.
Date of Payment Claim: The due date is calculated from the date when the payment claim is served, not the date written on the claim itself.
Payment Terms: This field on your project setup determines the contractual payment period that may override statutory timeframes if it results in an earlier date.
8. Frequently Asked Questions
Eliminate Due Date Errors
Our automated system ensures your payment claims are always compliant, calculating the correct due date every time.
Schedule DemoContract Administration for NSW Construction
Our team provides strategic contract administration and project management services that streamline your workflows, improve cash flow, and reduce compliance risks.
Serving: Residential builders, commercial subcontractors, and developers across NSW construction projects
Schedule Demo