Description of Construction Work - Cost Plus Payment Claim Best Practices | Contracts Administrator

Description of Construction Work in Cost Plus Payment Claims

📅 Updated: August 2025 ⏱️ 8 min read 📋 Cost Plus Payment Claim Best Practices

⚠️ Compliance Warning

An inadequate description of construction work is a primary cause of payment disputes and can lead to your entire claim being deemed invalid under the Security of Payment Act.

1. Field Name and Definition

The "Description of construction work" field is a crucial component of any NSW Cost Plus Payment Claim. This field requires a clear and detailed explanation of the construction work performed or related goods and services supplied during the relevant period covered by the payment claim. It must provide sufficient detail to identify the scope of work for which payment is being claimed.

This field appears on a Cost Plus Payment Claim because it forms part of the fundamental requirements for a valid payment claim under the Building and Construction Industry Security of Payment Act 1999 NSW (the Act). The description serves as the basis for the claimed amount and enables the respondent to understand exactly what they are being asked to pay for.

3. Practical Guidance

Step-by-Step Instructions

  1. Identify the relevant period: Clearly state the period during which the work was performed (e.g., "Work performed from 1 July 2025 to 31 July 2025").
  2. List all construction work performed: Provide a comprehensive list of all construction work carried out during the relevant period.
  3. Detail the scope: For each item of work, include specific details such as location, materials used, quantity of work (measurements, areas, volumes), and work stages completed.
  4. Include related goods and services: List any related goods supplied or services provided, such as materials delivered, design services, or equipment hire.
  5. Cross-reference with contract documents: Refer to relevant contract documents, drawings, or specifications where appropriate.
  6. Support with documentation: Attach supporting documentation where available, such as site diaries, progress photographs, and delivery dockets.

Where to Find This Information

The information required to complete this field can typically be found in:

  • Daily site records and progress reports
  • Project schedules and programs
  • Variation orders and instructions
  • Material delivery records and timesheets
  • Contract documents, including drawings and specifications

4. Common Mistakes and How to Avoid Them

Typical Errors

  • Vague descriptions: Simply stating "Construction work as per contract" or "Concreting works" without further detail.
  • Inconsistent terminology: Using different terms than those used in contract documents.
  • Incomplete scope: Failing to include all elements of work performed during the claim period.
  • Combining multiple periods: Failing to clearly separate work performed in the current claim period from previous periods.

Impact on Validity

Courts have held that "works must be sufficiently identified in the payment claim and 'it is not up to the recipient to sort through previous payment claims to ascertain work to which a new payment claim related'." Inadequate descriptions can lead to the entire claim being deemed invalid, parts of the claim being severed, and delayed payment while clarifications are sought.

Best Practices

  1. Be specific and comprehensive.
  2. Use consistent terminology from contract documents.
  3. Include quantities, measurements, and percentages.
  4. Organise information logically (e.g., by location, trade, or chronologically).
  5. Cross-reference with contract documents and include supporting documentation.

5. Risks of Not Including This Information

Failing to provide a clear and detailed description of work carries significant risks that can jeopardise your payment and create costly disputes.

Risk Type Consequence
Legal Risks Invalidation of the payment claim, rendering it unenforceable under the Act.
Financial Risks Delayed payment, partial payment due to severed items, or complete rejection of the claim.
Dispute Risks Increased likelihood of disputes requiring adjudication and challenges in proving entitlement.
Strategic Disadvantages Weaker position in adjudication proceedings and reduced leverage in negotiations.
Long-term Implications Damaged client relationships and the administrative burden of resubmission.

6. Examples

Example 1: General Building Work

Description of construction work:
For the period 1 July to 31 July 2025:
- Basement excavation: Removal of 120m³ of soil to a depth of 3.5m as per Drawing B-001.
- Footings: Installation of 24 reinforced concrete pier footings (600x600x800mm) as per Drawing S-002.
- Formwork: Installation of 85m² of formwork for ground floor slab as per Drawing S-003.
- Reinforcement: Supply and installation of 2.4 tonnes of reinforcing steel to ground floor slab as per Drawing S-004.
- Concrete: Supply and pour of 45m³ of 32MPa concrete to ground floor slab as per Drawing S-003.
- Site clean-up: Removal of excavation materials and general site clean-up.

Example 2: Renovation Work

Description of construction work:
For the period 15 July to 14 August 2025:
- Demolition: Removal of internal non-load bearing walls on Level 2 (120m²) as per Drawing A-101.
- Electrical: Rough-in of electrical services to Level 2 including installation of 18 power points, 12 light fittings, and 3 data points as per Drawing E-201.
- Plumbing: Rough-in of hydraulic services to Level 2 bathrooms including water supply and drainage as per Drawing H-101.
- Wall framing: Installation of 85m² of timber stud walls to Level 2 as per Drawing A-102.
- Plastering: Supply and installation of 170m² of plasterboard (walls) and 65m² (ceilings) to Level 2.

8. Frequently Asked Questions

Q1: How detailed should the description of construction work be?
A: The description must be sufficiently detailed to allow the respondent to understand what work is being claimed. Include specific locations, quantities, and references to contract documents where possible. A good rule of thumb is that someone unfamiliar with the project should be able to understand what work has been completed based on your description.
Q2: Can I group similar items together in my description?
A: Yes, you can group similar items, but ensure that each group is clearly described and quantified. For example, instead of listing each electrical outlet separately, you might state "Installation of 24 electrical outlets to Level 1 as per Drawing E-101."
Q3: If I've claimed for the same type of work in a previous payment claim, do I need to describe it again?
A: Yes, each payment claim must stand alone and include a proper description of all work being claimed for that period, even if similar work was described in previous claims. You must clearly identify what portion of the work is being claimed in the current period.
Q4: What if the work I've performed doesn't exactly match the contract documents?
A: Any variations from the contract should be clearly identified and described separately. Include references to variation approvals, site instructions, or other documentation authorising the changes.
Q5: Is it sufficient to attach invoices instead of providing a detailed description?
A: No, invoices alone are not sufficient. While they can be included as supporting documentation, the payment claim itself must contain a clear description of the construction work. Invoices typically don't provide the level of detail required by the Act.

Ensure Every Claim is Clear and Compliant

Our automated system helps you generate perfectly detailed descriptions, reducing disputes and ensuring you get paid faster.

Schedule Demo
Standardised CTA Section

Contract Administration for NSW Construction

Our team provides strategic contract administration and project management services that streamline your workflows, improve cash flow, and reduce compliance risks.

Serving: Residential builders, commercial subcontractors, and developers across NSW construction projects

Schedule Demo