Date of the Payment Claim - Cost Plus Best Practices | Contracts Administrator

Date of the Payment Claim in Cost Plus Payment Claims

📅 Updated: March 2024 ⏱️ 8 min read 📋 Cost Plus Payment Claim Best Practices

⚠️ Compliance Warning

Serving a payment claim outside the statutory 12-month limitation period renders the entire claim invalid, resulting in a loss of rights under the Act and significant cash flow prejudice.

1. Field Name and Definition

Date of the Payment Claim is the specific calendar date when a Payment Claim is issued or served on the person liable to make payment. This date establishes the precise commencement of all statutory timelines under the Building and Construction Industry Security of Payment Act 1999 NSW (the Act).

This field appears on every Payment Claim because it serves as the critical timestamp that triggers the respondent's obligation to provide a Payment Schedule within 10 business days and establishes the foundation for all subsequent enforcement actions under the Act.

3. Practical Guidance

Step-by-Step Instructions

  1. Determine the Last Work Date: Identify when construction work was last carried out or related goods and services were last supplied.
  2. Check Contract Terms: Review your construction contract for any specific timing requirements for payment claims.
  3. Calculate Allowable Period: Ensure the claim date falls within either the contractual period or 12 months from last work, whichever is later.
  4. Select Appropriate Date: Choose a date that allows adequate time for claim preparation whilst remaining within statutory limits.
  5. Document the Date: Record the date in DD Month YYYY format (e.g., 15 March 2024).

Where to Find This Information

  • Site Diary Entries
  • Delivery Dockets
  • Timesheet Records
  • Construction Contract
  • Project Management Systems

4. Common Mistakes and How to Avoid Them

  • Pre-dating Claims: Attempting to backdate claims is fraudulent and voids the claim. Always use the actual date of service.
  • Missing the 12-Month Deadline: Failing to track when work was last completed can result in serving claims outside the statutory time limit. Use project management tools to track key dates.
  • Ignoring Contractual Requirements: Some contracts specify monthly claim dates. Adhere to these provisions to ensure validity.
  • Inconsistent Dating: Using different dates on supporting documentation versus the main claim creates ambiguity. Ensure all documents are consistent.

5. Risks of Not Including This Information

Risk Type Consequence
Legal Risks The claim is invalid and loses all statutory protections under the Act. Adjudicators will lack jurisdiction.
Financial Risks Significant delays in payment recovery, loss of interest, and disruption to project cash flow.
Dispute Risks Claims face immediate dismissal at adjudication. Respondents will challenge validity based on dating errors.
Long-term Risks Damaged client relationships and a reputation for poor contract administration.

6. Examples

Properly Completed Examples

✅ Standard Progress Claim:
Date of Payment Claim: 15 April 2024
(Work was completed on 10 April 2024 and contract allows monthly claims)
✅ Final Claim:
Date of Payment Claim: 22 March 2025
(Last work was completed on 15 March 2024, within the 12-month limit)

8. Frequently Asked Questions

Q: Can I change the date on a Payment Claim after it has been served?

A: No. Once served, the date cannot be changed as it establishes all statutory timelines. If you discover an error, you must withdraw the claim and serve a new, correctly dated one if the time limits still permit.

Q: What happens if I accidentally serve a Payment Claim outside the 12-month limit?

A: The Payment Claim is invalid and cannot be enforced under the Act. You lose the right to claim payment for that work through the statutory process, though you may still have rights under general contract law.

Q: How do I prove the date I served the Payment Claim?

A: Maintain detailed records of service, such as postal receipts, email delivery confirmations, or signed delivery acknowledgements. Digital timestamps provide the strongest evidence.

Never Miss a Deadline Again

Ensure every payment claim is perfectly timed and fully compliant with our automated contract administration platform.

Get Started Today
Standardised CTA Section

Contract Administration for NSW Construction

Our team provides strategic contract administration and project management services that streamline your workflows, improve cash flow, and reduce compliance risks.

Serving: Residential builders, commercial subcontractors, and developers across NSW construction projects

Schedule Demo